Question 1
Which item is a formal proposal to modify any document, deliverable, or baseline?
  1. Change request
  2. Requirements documentation
  3. Scope baseline
  4. Risk urgency assessment
Correct answer: A
Question 2
Which process determines the risks that may affect the project and documents their characteristics?
  1. Control Risks
  2. Plan Risk Management
  3. Plan Risk Responses
  4. Identify Risks
Correct answer: D
Question 3
An example of a group decision-making technique is:
  1. Nominal group technique.
  2. Majority.
  3. Affinity diagram.
  4. Multi-criteria decision analysis.
Correct answer: B
Question 4
A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
  1. mitigate
  2. accept
  3. transfer
  4. avoid
Correct answer: C
Question 5
An output of the Plan Quality Management process is:
  1. A process improvement plan,
  2. Quality control measurements.
  3. Work performance information,
  4. The project management plan.
Correct answer: A
Question 6
A project manager should document the escalation path for unresolved project risks in the:
  1. Change control plan
  2. Stakeholder register
  3. Risk log
  4. Communications management plan
Correct answer: D
Question 7
Which process in Project Time Management includes reserve analysis as a tool or technique?
  1. Estimate Activity Resources
  2. Sequence Activities
  3. Estimate Activity Durations
  4. Develop Schedule
Correct answer: C
Question 8
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
  1. Enhance
  2. Share
  3. Exploit
  4. Accept
Correct answer: C
Question 9
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
  1. Expert judgment.
  2. Analytical techniques.
  3. Earned value management.
  4. Group decision-making techniques.
Correct answer: B
Question 10
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
  1. Timing
  2. Methodology
  3. Risk categories
  4. Budgeting
Correct answer: A
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!